Projects



Current Capital Projects in 2023

Installation and upgrade of (12) fuel stations at various locations in the Kingdom.

 Installation a new solar system (PV) for LPG Filling Stations (Amman & Irbid) at a cost of around (900) thousands JD.

Supply and install a new CCTV system for LPG Filling Stations (Amman & Irbid) at a cost of around (320) thousands JD.

Installation of LPG storage facilities with capacity of 10000 MT at a cost of around (50) million JD

 Supply and installation a new water spray washing machines (Capacity 12.5 Kg) for Amman LPG Filling Station at a cost of around (400) thousands JD.

 Design, supply and commissioning of new water treatment unit with capacity 120 m2/hour for (Well No. 12) at a cost of around (950) thousands JD.

Installation of firefighting and alarm systems in Aqaba South installations at a cost of around (800) thousands JD. 81

 Purchasing a fire fighting vehicle at a cost of around (400) JD

 Upgrading of the fire-fighting water network in crude oil receiving station by constructing new above ground network with at a cost of around (300) thousands JD.

 Purchasing special valves (remotely operated) for LPG spheres in Aqaba south installations at a cost of around (250) thousands JD.

 Purchasing (10) radar gauges for petroleum tanks at a cost of around (250) thousand JD.

 Installation of firefighting and alarm systems in crude oil receiving station and jet fuel filtration system a cost of around (250) thousands JD.

 Purchasing two Inter–Stage Condensate pump for FCC unit at a cost of around (250) thousands JD

 Re-habitation of drainage system and maintenance works on concrete slabs in chemical treatment unit at a cost of around (180) thousands JD.

 Purchasing (35) temperature measurement instruments for tanks at a cost of around (150) thousands JD.

 Purchasing (4) testing instruments for refinery units at a cost of around (110) thousands JD.

 Purchasing (5) pick-up vehicles at a cost of around (100) thousands JD.

 Purchasing two LCO Circulation pumps for FCC unit at a cost of around (100) thousands JD.

 Replacing of tank no. 27 (Diesel Cycle Oil) at a cost of around (100) thousands JD.

 Purchasing (4) eclectic motors (400 V) and its control panels with VSD at a cost of around (85) thousands JD.

 Installation of (4) elevators for residential area at a cost of around (80) thousands JD.

 Purchasing humidity measuring device for circulating gas in platforming unit at a cost of around (70) thousands JD

 Installation of Euro (5) receiving station at a cost of around (50) thousands JD.

 Installation of fire fighting system in loading department offices at a cost of around (50) thousand JD.

 Installation of store for chemicals at a cost of around (40) thousands JD.