The most important capital projects that have been completed during the year 2022:

Completion of construction and upgrading of (20) fuel stations throughout the Kingdom

Purchase of new LPG cylinder foot ring straightener machine LPG Cylinders' repair and rehabilitation workshop at a cost of around (25) thousands JD

Supply and installation of test pits for LPG cylinders (Capacity 12.5 KG) for LPG Filling Stations (Zarqa, Amman & Irbid) at a cost of around (65) thousands JD.

Supply a new hydrostatic test machine for LPG cylinders (Capacity 12.5 KG) at a cost of around (80) thousands JD.

Supply a new LPG cylinder crushing machines (2 Numbers) at a cost of around (30) thousands JD.

Upgrading of the fire-fighting water network in crude oil receiving Station by constructing new above ground network with at a cost of around (300) thousands JD.

Upgrading the DCS controlling system software for LPG sphere tanks at a cost of around (250) thousands JD.

Installation of New Pipeline to Transfer Euro5 Diesel at Refinery Site at an estimated cost of around (100) thousands JD.

Purchase of a new pressure vessel to replace existing old one in FCC unit at an estimated cost of around (90) thousands JD.

Purchase four electrical motors (400V) at an estimated cost of around (85) thousands JD.

Purchase of new pressure vessel to replace old one at an estimated cost of around (80) thousands JD.

 Purchase of a new pressure vessel to replace existing old one in FCC unit at an estimated cost of around (80) thousands JD.

Upgrade the level gauge equipment relevant to high pressure vessels in Unibon Unit at an estimated cost of around (70) thousands JD.

 Construction of new firefighting network to cover several areas (flare, fire test station, area located on east side of SRU and oil sludge pets), at an estimated cost of around (60) thousands JD.

Purchase a new three pick-ups vehicles at an estimated cost of around (60) thousands JD.

 Upgrade the protection and alarm system (Pre-Alarm System) for N.H.T and Unibon compressors at an estimated cost of around (50) thousands JD.

Purchase a new EDXRF device to check sulfur in crude oil and related products at an estimated cost of around (45) thousands JD.

 Purchase a new electrical motor for Boiler Feed water Pump at an estimated cost of around (35) thousands JD.

 Purchase of Caustic Pump for chemical treatment unit at an estimated cost of around (30) thousands JD.

Supply of air blower for soot blowers heater at an estimated cost of around (20) thousands JD.